📞 022 4302 0000contact@takemyinsurance.com
Register|LoginJoin us as POSP
AboutWhat Is CoveredSum InsuredALOP vs CARWho Needs ItClaim ProcessExclusionsFAQsGet Quote Page Progress  0%
🏗 Engineering Insurance · Project Finance · Infrastructure · Power · Industrial · Capital Projects

Advance Loss of Profit Insurance (ALOP) — Revenue & Profit Protection When a Capital Project Is Delayed by Insured Damage —
Loss of Gross Profit · Standing Charges · Debt Service · Increased Cost of Working · Liquidated Damages

A Contractor’s All Risk or Erection All Risk policy covers only the cost of repairing physical damage to a project under construction. It does not cover the revenue, profit, and fixed charges that the project owner loses every day that commissioning is delayed. Advance Loss of Profit Insurance bridges this gap — protecting the anticipated gross profit, standing charges, debt service costs, and increased working costs that accrue during a delay period caused by an insured physical damage event under the underlying construction or erection policy.

✓ Loss of Gross Profit ✓ Standing Charges ✓ Debt Service / Interest ✓ Increased Cost of Working ✓ Liquidated Damages Exposure ✓ CAR / EAR / MCE Linked
Engineering Insurance · Project Finance · Infrastructure · Power · EPC Contractors · Lenders  |  IRDAI Licensed Broker — Lic. No. 528
ALOP
🏛IRDAI Licensed Broker · Lic. No. 528
🏗Gross Profit · Standing Charges · Debt Service · LD Exposure · Increased Cost of Working
📈CAR / EAR / MCE Linked · Infrastructure · Power · Industrial ProjectsLender Requirement
📞Specialist Enquiry 022 4302 0000
An IRDAI Licensed Insurance Broker

Engineering Insurance · Project Finance · Construction · Infrastructure · Power · Industrial Capital Projects

What Is Advance Loss of Profit (ALOP) Insurance?

Advance Loss of Profit Insurance — commonly called ALOP, Delay in Start-Up (DSU) insurance, or Consequential Loss — Engineering insurance is a specialised policy that covers the financial loss a project owner suffers when the commercial commissioning of a capital project is delayed because of physical damage covered under the underlying construction or erection insurance policy. While a Contractor’s All Risk (CAR), Erection All Risk (EAR), or Marine-cum-Erection (MCE) policy pays the cost of repairing or replacing the physically damaged property, ALOP covers the revenue and profit losses that accumulate during every day of delay — the lost income, the fixed charges that continue regardless of production, debt servicing costs, and penalties that cannot be avoided during the delay period.

🏗

The Gap That ALOP Fills — Why Physical Damage Cover Alone Is Not Enough

Consider a 100 MW solar power plant under construction in Rajasthan. The developer has invested ₹500 crore and has committed to commence supply to a state discoom under a Power Purchase Agreement (PPA) from 1 April 2026. In December 2025, a fire destroys the main transformer yard, causing physical damage of ₹15 crore.

  • What the CAR policy pays:The ₹15 crore cost of repairing and replacing the damaged transformers and switchyard equipment — the direct physical loss only.
  • What the CAR policy does NOT pay:The 4-month delay in commissioning while the equipment is re-ordered, re-imported, and re-installed. During those 4 months: the developer cannot generate or sell electricity (lost revenue), the debt service on the ₹350 crore project loan continues (₹8–10 crore in interest), O&M costs begin accruing even before revenue starts, and liquidated damages under the PPA for delayed commercial operation may be triggered.
  • What the ALOP policy pays:The actual loss of anticipated gross profit and standing charges (including debt service, O&M fixed costs, and interest) during the 4-month delay period — the financial consequence of the delay, not the physical repair cost.

ALOP and CAR/EAR policies together provide complete project protection: physical damage is covered by CAR/EAR, and the financial consequence of delay is covered by ALOP.

Key Features of ALOP Insurance
💰

Loss of Gross Profit

Covers net profit plus standing charges (fixed costs) that would have been earned during the delay period, calculated on the basis of anticipated turnover from the commissioned project.

PROFIT
🕑

Indemnity Period

The maximum period for which the policy pays — selected at inception based on the worst-case time needed to re-import, re-erect, and re-test any critical component. Typically 12–36 months.

PERIOD

Increased Cost of Working

Covers additional expediting costs — airfreight instead of sea freight, overtime labour, premium supplier rates — incurred to shorten the delay period and reduce the overall loss.

ICOW
📈

Debt Service / Interest

Covers interest charges and loan repayments that continue during the delay period even though the project is not yet generating revenue — a critical exposure for leveraged project finance structures.

DEBT

Linked to Underlying Policy

ALOP responds only when there is a valid, payable claim under the underlying CAR, EAR, or MCE policy. No physical damage claim = no ALOP claim. The two policies must be co-ordinated.

LINKED
🏠

Lender / Lessee Requirement

Project finance lenders routinely require ALOP as a condition of project loan drawdown. Build-Operate-Transfer (BOT) concession agreements and Power Purchase Agreements (PPAs) may mandate it.

LENDERS

What ALOP Insurance Covers — Covered Losses and Key Definitions

What Is Covered Under ALOP Insurance?

ALOP insurance covers the financial consequences of delay in project commissioning arising from an insured physical damage event under the underlying engineering policy. The coverage is structured around the concept of Gross Profit — which has a specific technical definition in this context.

Covered Financial Losses

  • Loss of Gross Profit (Net Profit + Standing Charges):The primary coverage. Gross Profit = Net Profit + Standing Charges. Net Profit is business profit before taxation that would have been earned if the project had commissioned on schedule. Standing Charges are fixed costs that continue during the delay regardless of whether the project is operational — salary and wages, director fees, lease rentals, maintenance costs, management fees.
  • Loss of Gross Earnings (Turnover minus Specified Working Expenses):An alternative basis used primarily for projects where net profit is uncertain or negative in early years. Gross Earnings = Total Turnover minus the specific variable costs directly avoided by not operating. This approach is common for manufacturing projects in their ramp-up phase.
  • Fixed Operation & Management Costs:Fixed O&M costs that the project owner is contractually committed to paying — O&M contracts, facility management agreements — even before the project generates revenue.
  • Debt Service Charges:Interest on project finance loans, scheduled principal repayments, and commitment fees that accrue during the delay period regardless of whether the project is earning revenue. This is often the most significant single item in an ALOP claim for a leveraged project.
  • Increased Cost of Working (ICOW):Additional expenditure necessarily and reasonably incurred to avoid or reduce the delay — airfreighting equipment instead of shipping, working double shifts, paying premium prices to expedite replacement components. ICOW is covered to the extent it reduces the overall ALOP claim.
  • Special Expenses & Penalties:Liquidated damages payable under the Power Purchase Agreement, off-take agreement, or construction contract for delay in commercial operation — including penalties imposed by the off-taker or concession authority for failure to achieve commissioning milestones.

What Is NOT Covered (Key Exclusions)

  • Delay not caused by a payable CAR/EAR claim:ALOP responds only when the delay arises from physical damage that gives rise to a valid claim under the underlying CAR, EAR, or MCE policy. If the physical damage is excluded under the CAR policy (e.g. excluded defective design), ALOP does not respond either.
  • Inventory losses:Loss of raw materials, components, or finished goods inventory is not a delay in commissioning event and is excluded from ALOP coverage. These losses may be covered under the CAR policy as property damage.
  • Delay in shipment of supplies:Delay caused by supplier failure, shipping schedule slippage, or late delivery of equipment — where no physical damage has occurred — is not covered. Only delay caused by physical damage triggering the underlying policy is insurable.
  • Normal project schedule slippages:Baseline delays arising from construction inefficiency, planning failures, labour shortages, or normal schedule overruns that are not caused by a specific physical damage event are excluded.
  • Non-availability of funds for repair:If the project owner cannot repair the damage because they lack funds to do so — even if the physical damage is covered — the consequent delay is not covered by ALOP as a stand-alone delay cause.
  • Cancellation of licence or government restrictions:Regulatory revocation, government policy changes, licence cancellations, and environmental clearance withdrawals that delay commissioning independently of any physical damage are excluded.
  • Time excess (deductible):ALOP policies have a time excess — typically 30, 60, or 90 days — meaning the insured bears the first period of delay before the policy begins paying. This is the temporal equivalent of a monetary deductible.

How to Calculate the Correct Sum Insured and Select the Indemnity Period

Sum Insured & Indemnity Period — Getting It Right

Correct sum insured calculation is the most technically demanding aspect of ALOP insurance. Underinsurance at the time of a claim results in proportionate claim reduction. The sum insured must represent the anticipated gross profit for the full indemnity period selected.

📈

The Sum Insured Formula — Anticipated Gross Profit for the Indemnity Period

The sum insured should represent: Anticipated Gross Profit × Indemnity Period (in months) / 12

Where Anticipated Gross Profit = Net Profit + Standing Charges for the first full year of operation.

Net Profit = Projected business profit before taxation, based on the financial model for the project. For a power plant: anticipated revenue from electricity sales minus variable O&M costs and fuel costs.

Standing Charges = All fixed costs that continue regardless of whether the project operates during the delay: interest on project loans, salary and wages, director and management fees, fixed O&M contract costs, insurance premiums, lease rentals, property taxes, audit and legal fees.

Example (100 MW Solar Power Plant):
Anticipated annual revenue: ₹70 crore
Variable O&M costs: ₹3 crore/year
Net Profit = ₹67 crore
Standing Charges (debt service + fixed O&M + admin): ₹25 crore/year
Anticipated Gross Profit = ₹67 + ₹25 = ₹92 crore/year
Indemnity Period: 18 months
Sum Insured = ₹92 crore × 18/12 = ₹138 crore

🕑

Indemnity Period Selection — The Most Critical Decision

The Indemnity Period is the maximum duration for which the ALOP policy will pay — measured from the scheduled commercial operation date (COD). Once the indemnity period expires, no further ALOP payments are made regardless of whether the delay continues.

How to select the right indemnity period:
The indemnity period should cover the worst-case scenario for the longest possible delay arising from the most critical single-point-of-failure component in the project. Ask: "What is the single item in this project that, if damaged, would take the longest to source, ship, and reinstall?" For most large infrastructure projects, this analysis typically identifies:

Power transformers (large custom units): 12–24 months lead time to manufacture, test, and deliver
Gas turbines (bespoke large units): 18–36 months from order to commissioning
Boilers and pressure vessels: 12–18 months
Specialised rotating equipment: 6–18 months
Marine foundations (offshore wind): 12–24 months

The indemnity period should be set at least equal to the replacement lead time of the longest-lead critical item. Under-selection of indemnity period is the most common error in ALOP placement and leaves significant uninsured exposure.

Common selections: 12 months (small projects), 18 months (standard industrial), 24 months (large infrastructure), 36 months (mega projects with very long-lead equipment).

Time Excess — The Policy’s Time Deductible

ALOP policies always include a Time Excess — the initial period of delay that the insured bears before the policy begins paying. Common time excesses are 30, 60, or 90 days.

The time excess choice affects both the premium and the insured’s retained risk:
• A 30-day time excess means the insured bears the first month of delay loss themselves; the policy pays from day 31
• A 90-day time excess reduces the premium significantly but means the insured self-retains all losses for the first 3 months of any delay

For projects with strong cash reserves or where short delays would be manageable, a higher time excess (60–90 days) reduces premium cost. For leveraged projects with tight debt service obligations, a lower time excess (30 days) provides earlier policy response and is typically required by lenders.

Note: The time excess is measured from the actual date the project was scheduled to commence commercial operation, not from the date of the physical damage event.

💰

Underinsurance Risk — The Average Condition

ALOP policies are subject to the average condition (co-insurance clause). If the sum insured at the time of the claim is less than the actual anticipated gross profit for the indemnity period, the claim settlement will be reduced proportionately.

Example: Sum insured = ₹100 crore. Actual anticipated gross profit = ₹150 crore. Claim assessed at ₹30 crore. Settlement = ₹30 crore × (₹100 / ₹150) = ₹20 crore — the insured effectively self-retains ₹10 crore due to underinsurance.

Underinsurance in ALOP frequently arises from: using outdated financial models that do not reflect PPA price revisions, failing to include all standing charges (particularly all-in debt service), selecting an indemnity period that is too short, and not updating the sum insured when project scope or financing changes during the construction period. Annual review of the ALOP sum insured during the construction period is strongly recommended.

Understanding How ALOP and CAR / EAR Policies Work Together

ALOP Insurance vs CAR / EAR / MCE — Complete Project Protection

ALOP is always a companion policy to an underlying engineering policy — never a standalone product. The two must be co-ordinated at placement to ensure there are no gaps in coverage and that the trigger, exclusions, and indemnity periods are properly aligned.

📋

CAR / EAR vs ALOP — The Complete Picture

AspectCAR / EAR / MCE PolicyALOP Policy
What it coversCost of repairing or replacing physically damaged propertyFinancial loss from delay in commercial commissioning
Loss basisReinstatement / replacement cost of damaged itemsAnticipated gross profit per day × number of delay days
Deductible structureMonetary deductible (e.g. ₹50 lakh per event)Time excess (e.g. 30/60/90 days)
TriggerAccidental physical loss or damage during constructionDelay caused by a payable CAR/EAR claim event
Period of coverConstruction period until commissioning / testingFrom scheduled COD to actual COD (up to indemnity period)
Sum insured basisContract value / replacement cost of project assetsAnticipated gross profit × indemnity period
Who is the insuredPrincipal, main contractor, sub-contractors, lendersPrincipal / project company (the revenue earner)
Lender interestLenders noted as additional insured / loss payeeLenders typically require ALOP as a loan condition
IndependenceCan stand alone without ALOPCannot respond without an underlying payable CAR/EAR claim

The Co-ordination Imperative — Why ALOP and CAR Must Be Placed Together

ALOP and CAR/EAR policies must be placed with co-ordinated terms to avoid coverage gaps. Key co-ordination requirements:

Exclusions alignment: Any exclusion in the CAR policy (e.g. defective design, faulty workmanship) should be reviewed in the context of ALOP — since ALOP only responds when the CAR claim is payable, a broad CAR exclusion can inadvertently eliminate ALOP coverage too.
Territorial scope: Both policies should cover the same geographic scope — particularly important for projects with equipment sourced internationally (marine-cum-erection structure).
Insured parties: The principal/project company must be insured under both policies to make ALOP claims.
Policy period: The ALOP period should extend beyond the CAR period to cover delays materialising at the end of the construction period.

Probitas provides specialist co-ordination of CAR and ALOP placement for project finance transactions. Call 022 4302 0000.

Which Projects, Principals, and Lenders Require ALOP Insurance

Who Should Buy ALOP Insurance?

ALOP is most relevant for capital-intensive projects where a construction delay causes significant, quantifiable revenue loss and where fixed financial obligations (debt service, fixed costs) continue during the delay period.

Project Types Where ALOP Is Essential

  • Power generation projects:Thermal, solar, wind, hydro, and nuclear power plants are the most common ALOP buyers. The combination of long-lead equipment (transformers, turbines, boilers), project finance debt, and PPA-linked revenue makes ALOP essential. Any delay in COD means lost PPA revenue and continuing debt service — a severe cash flow mismatch.
  • Renewable energy (solar and wind):Large-scale solar parks and wind farms have become the dominant segment for ALOP in India following the surge in renewable capacity additions. PPA commitments, generation-linked debt amortisation, and the risk of transformer or substation damage make ALOP a standard requirement in renewable energy project finance.
  • Oil, gas, and petrochemical plants:Refineries, LNG terminals, gas processing plants, and petrochemical facilities have high replacement costs, very long equipment lead times, and operate under off-take agreements — all factors that make delay losses severe and ALOP essential.
  • Manufacturing and industrial facilities:Steel mills, cement plants, automotive manufacturing facilities, pharmaceutical API plants, and other large industrial projects have significant project finance structures and fixed operating cost commitments that create ALOP exposure.
  • Infrastructure (toll roads, bridges, airports, ports):Concession-based infrastructure projects operating under BOT or PPP agreements face revenue loss from commissioning delays and may face concession period shortening — an indirect financial consequence of delay that ALOP can be structured to cover.
  • Transmission and distribution infrastructure:High-voltage transmission lines, substations, and distribution network investments have very high equipment values (especially HV transformers) and clear commissioning milestones linked to connection agreements and grid codes.
🏠

Who Takes Out the ALOP Policy?

  • The Principal / Project Company:ALOP is taken by the principal — the entity that will own and operate the completed project and that stands to lose revenue from any delay in commissioning. EPC contractors and sub-contractors are not the right insured for ALOP (they may have separate LD covers); the project company that will earn the PPA revenue or production income is the correct ALOP buyer.
  • Project finance lenders (as additional insured):Banks and financial institutions providing project finance loans routinely require ALOP as a condition of loan drawdown. Lenders are noted as additional insured or loss payee to ensure ALOP proceeds are available for debt service in the event of a delay. The loan agreement will typically specify minimum ALOP coverage requirements.
  • Off-takers and concession authorities:In some project structures, the off-taker (state discoom, NTPC, SECI) or concession grantor may have an interest in the ALOP policy to protect their off-take agreement and ensure the project comes online on schedule.
  • Build-Operate-Transfer (BOT) project developers:Developers of BOT infrastructure projects (toll roads, ports, airports) that earn revenue based on a concession period have a specific ALOP exposure: delay in commissioning shortens the effective revenue-generating period of the concession.
  • EPC contractors with delay penalties:While EPC contractors are not the natural ALOP buyer (the project company is), contractors who face severe liquidated damage exposure for delay may need to consider their own financial protection, which may be structured separately from the project company’s ALOP.

How an ALOP Insurance Claim Works — From Damage Event to Settlement

ALOP Claim Process

ALOP claims are complex and require specialist loss adjustment. The ALOP claim can only proceed in conjunction with the underlying CAR/EAR claim and requires detailed financial documentation.

🚨

Step 1 — Report the Physical Damage Immediately

The ALOP claim process begins with a physical damage event under the CAR/EAR/MCE policy:
• Notify Probitas (022 4302 0000) and the CAR/EAR insurer immediately upon occurrence of significant physical damage
• Preserve evidence of the damage — photographs, site reports, contractor incident reports
• Do not commence repair without surveyor attendance for significant losses
• Simultaneously notify the ALOP insurer (usually a co-ordinated notification)
• Issue a formal delay notification to the off-taker, lender, and concession authority as required under the PPA/loan agreement

The date of the physical damage event is critical as it establishes the start of the delay calculation and the reference point for the time excess measurement.

📋

Step 2 — Establish the Physical Damage Claim

The ALOP claim cannot proceed until the CAR/EAR claim is admitted:
• A property damage surveyor assesses the physical damage under the CAR/EAR policy
• The scope and cost of repairs is established
• The CAR/EAR insurer confirms the damage is a valid, payable claim (not excluded)
• The projected repair timeline is documented by the contractor and equipment supplier

Throughout this stage, Probitas co-ordinates between the CAR/EAR surveyor and the ALOP loss adjuster to ensure consistent findings on the cause of damage, which is the common trigger for both policies.

Key documentation at this stage: Contractor’s incident report, surveyor’s inspection report, equipment manufacturer’s damage assessment, initial repair timeline estimate from contractor, correspondence with equipment suppliers about replacement lead times.

📈

Step 3 — Quantify the Delay Period and Financial Loss

Once the physical damage claim is established, a specialist ALOP loss adjuster (usually a forensic accountant with engineering project experience) is appointed to quantify the financial loss:

Establish the scheduled COD: Documented in the EPC contract, PPA, or loan agreement — the date the project was contractually required to begin commercial operation
Establish the actual COD: The date the project actually achieved commercial operation after repairs
Calculate the delay period: Actual COD minus Scheduled COD, less the time excess
Calculate daily loss: Anticipated Gross Profit / 365 = daily loss rate
Assess ICOW: Review additional costs incurred to shorten the delay — airfreight, overtime, expediting premiums
Cross-check sum insured adequacy: Verify whether the sum insured is adequate for the actual gross profit, or whether underinsurance applies

Financial documentation required: PPA or off-take agreement, audited financial projections, project financial model (base case), loan agreement (for debt service quantification), contractor’s revised project schedule, invoices for ICOW expenditures.

Step 4 — Interim Payments and Final Settlement

For long delay periods, ALOP policies typically allow for interim payments:
• As the delay period accumulates, interim ALOP payments can be requested periodically (typically quarterly or at agreed milestones)
• Interim payments are made on account of the final settlement, subject to final reconciliation
• Probitas manages the interim payment requests and supports the loss adjuster with financial data

Final settlement:
• Agreed once the actual COD is achieved and the final delay period is confirmed
• Final settlement = (Actual Delay Days − Time Excess Days) × Daily Loss Rate, plus agreed ICOW, subject to sum insured cap and any underinsurance adjustment
• Payment is made to the principal and/or lenders as specified in the policy

ALOP claims are typically the most complex and long-running claims in the engineering insurance class. Probitas’s specialist claims advocacy role is critical throughout the process.

What ALOP Insurance Does Not Cover

Key Exclusions — ALOP Insurance

ALOP exclusions are critically important because they define when the policy does not respond despite a delay occurring. Understanding these is essential for project risk management.

❌ No Payable CAR/EAR Claim

If the delay-causing damage is excluded under the underlying CAR/EAR policy (e.g. excluded defective design, faulty workmanship exclusion applied), ALOP cannot respond. The CAR/EAR trigger is a prerequisite.

❌ Inventory Losses

Loss of raw materials, consumables, or finished goods stored at site. These are property damage items that may be covered under CAR but are not a commissioning delay cause for ALOP purposes.

❌ Shipping / Supply Delays

Delay in shipment of replacement equipment, materials, or supplies — where no physical damage to the project has occurred — is not an ALOP trigger. Only damage-caused delay is covered.

❌ Normal Schedule Slippages

Baseline schedule overruns from construction inefficiency, poor planning, labour shortages, and normal project execution delays not caused by any specific physical damage event.

❌ Funding Unavailability

Delay in repair because funds are not available to purchase replacement equipment — even though the physical damage is covered — is not a covered delay cause under the ALOP policy.

❌ Regulatory / Government Action

Delay from revocation of environmental clearance, cancellation of grid connection permission, change in government policy, or any regulatory / administrative action by a government authority.

❌ Time Excess Period

The initial delay period (typically 30–90 days) falls entirely on the insured as the temporal deductible. No ALOP payment is made for delay days within the time excess period.

❌ Delay Beyond Indemnity Period

If the actual delay exceeds the selected indemnity period, ALOP payments cease at the end of the indemnity period. The insured bears all delay losses beyond the indemnity period cap.

📋

Important Disclaimer

The information and product comparisons displayed on this platform are intended solely for general informational and evaluation purposes, and do not constitute a legal offer or binding insurance contract. Specific policy features, premium rates, riders, and underwriting guidelines are determined exclusively by the respective general insurance carriers and may vary significantly based on the insurer, product tier, and location across multiple Indian states. All quotes and premium calculations generated on this website are indicative estimates based on preliminary data and do not guarantee final underwriting approval or policy issuance by the insurer. For comprehensive details regarding specific coverage terms, limits, and permanent exclusions, please refer directly to the official sales brochure and policy wording issued by the respective insurance company, which will take absolute legal precedence in the event of any discrepancy or dispute.

ALOP Insurance Questions

Frequently Asked Questions

ALOP and Business Interruption (BI) insurance are structurally similar — both cover consequential financial loss following a physical damage event — but they apply at different stages of a project or business. Business Interruption insurance protects an operating business against loss of revenue when a fire or other insured peril interrupts operations. The underlying policy is a Fire policy or Property All Risk policy covering the operating plant. ALOP insurance protects a project under construction against loss of anticipated revenue when damage delays the start of operations. The underlying policy is a CAR, EAR, or MCE engineering policy. Key distinction: BI covers interruption of existing operations (post-commissioning), while ALOP covers delay in commencement of new operations (pre-commissioning). A project typically needs ALOP during construction and BI after it enters commercial operation. The two periods are typically covered by different policies placed at different times.
Lenders typically specify minimum ALOP requirements in the loan agreement, including: minimum sum insured (often linked to the debt service reserve account or total outstanding debt), minimum indemnity period (often 18–24 months), maximum time excess (often 30–60 days), requirement for the lender to be noted as additional insured or loss payee, requirement for the insurer to have a minimum credit rating (typically A- or above from a recognised rating agency), and requirement for a letter of undertaking from the insurer to notify the lender before cancellation. Probitas can prepare a certificate of insurance and insurance summary for lender review, and can liaise with the lender’s insurance adviser during the due diligence process. Contact 022 4302 0000 to begin the placement process with lender requirements in mind.
ALOP premium is calculated as a percentage of the sum insured (anticipated gross profit for the indemnity period). The rate depends on: the type and complexity of the project (power vs manufacturing vs infrastructure), the indemnity period selected (longer = higher rate), the time excess (shorter = higher rate), the type and lead time of critical equipment (longer lead time = higher rate), the geographic location and natural catastrophe exposure, the insured’s project management and contractor quality, and the underlying CAR/EAR policy’s own terms and rating. ALOP rates in India for straightforward projects typically range from 0.1%–0.4% of the sum insured per year, but specialist projects (LNG, nuclear, offshore) can be significantly higher. For a solar project with a ₹100 crore ALOP sum insured and an 18-month indemnity period, the premium might range from ₹30–60 lakh total for the construction period. Call 022 4302 0000 for a specific rate indication based on your project details.
ALOP and CAR/EAR can technically be placed with different insurers, but this is generally not recommended and can create coverage gap risks. When placed with the same insurer (or at minimum co-ordinated through the same broker), the trigger alignment, exclusion language, and claims co-ordination are much cleaner. If placed with different insurers, the ALOP insurer will rely on the CAR insurer’s claims decision to admit or deny the ALOP trigger — which can create disputes if the CAR claim is only partially admitted. Probitas strongly recommends placing ALOP and CAR/EAR together to ensure: identical exclusion language, shared surveyor appointments, co-ordinated claims handling, and avoidance of the “gap” risk where a partially admitted CAR claim creates uncertainty in the ALOP trigger. Call 022 4302 0000 to discuss co-ordinated placement.
This is one of the most complex and disputed areas in ALOP claims. If the CAR claim is partially admitted (e.g. some damage is covered but damage attributable to defective design is excluded), the ALOP trigger may be debated. The outcome depends on the specific ALOP policy wording: some policies respond whenever any part of the delay-causing damage is payable under CAR; others require that the entire delay-causing event be covered. In practice, if the critical damage that caused the delay is excluded under CAR (e.g. a turbine rotor fails due to design defect — excluded — causing the delay), ALOP will typically not respond. If secondary damage covered by CAR (e.g. fire caused by the failed rotor) also causes delay, the covered-damage-caused delay portion may be recoverable. Co-ordination of CAR and ALOP exclusion language at placement is essential to minimise these disputes.
The daily loss rate for an ALOP claim is calculated as: Annual Anticipated Gross Profit ÷ 365 days. Annual Anticipated Gross Profit = Net Profit + Standing Charges for the first full year of operation, as projected in the financial model at the time of policy placement. Important considerations: (1) The rate may not be flat — projects in ramp-up phase have lower revenue in early months, so a monthly loss profile may be used rather than a flat daily rate. (2) The loss adjuster verifies the financial model projections against the PPA tariff, projected generation, and actual contracted costs. (3) Increased Cost of Working is added to the daily loss claim as separately documented. (4) If the actual gross profit forecast changes materially between policy placement and the claim, the sum insured adequacy test may apply (underinsurance check). Probitas assists policyholders in preparing the financial model and loss quantification for ALOP claims.
Yes — liquidated damages (LDs) payable to the off-taker under a PPA for delay in achieving the Scheduled Commercial Operation Date (SCOD) are a coverable item under ALOP as a “special expense.” However, coverage depends on: (1) the LD being specifically included as a covered item in the ALOP policy schedule; (2) the delay being caused by a covered physical damage event under the underlying CAR/EAR policy; (3) the LD being a genuine pre-estimated loss rather than a penalty under Indian contract law (penalties are not enforceable under Indian law, but genuine pre-estimated LDs are). When placing ALOP for a project with PPA LD exposure, the PPA LD structure, cap, and calculation must be disclosed to the insurer and specifically underwritten. Probitas ensures LD exposure is properly disclosed and covered at placement. Call 022 4302 0000.
ALOP insurance should ideally be placed at the same time as the CAR/EAR policy — at the commencement of physical construction or at the start of the erection period. Key timing considerations: (1) ALOP must be in place before a damage event occurs to be triggered by it — it cannot be placed retroactively. (2) Many lenders require evidence of ALOP placement as a condition of financial close — so placement must precede first loan drawdown. (3) If construction has been ongoing for some time without ALOP, the insurer may impose retrospective coverage conditions or exclude certain categories of equipment already at site. (4) The ALOP policy period should at minimum run until the latest possible COD under the EPC contract — typically the scheduled COD plus the full indemnity period. Probitas recommends placing ALOP as part of the initial project insurance programme during financial close. Contact 022 4302 0000 for specialist ALOP placement advice.

Specialist ALOP Insurance Enquiry

Advance Loss of Profit Insurance — Project Enquiry

ALOP insurance requires specialist underwriting and project-specific structuring. Share your project details and our engineering insurance specialist will contact you within 24 hours to discuss your ALOP placement requirements.

🏗 Organisation & Contact

⚡ Project Details

By submitting you agree to our Privacy Policy and Terms & Conditions. ALOP insurance is a specialist engineering product requiring detailed project information for underwriting. Terms, premium, and coverage are subject to underwriter review. Probitas Insurance Brokers Pvt. Ltd. · IRDAI Lic. No. 528.

🏗 Advance Loss of Profit (ALOP) Insurance — Complete Project Revenue Protection

Loss of Gross Profit · Standing Charges · Debt Service · Increased Cost of Working · Liquidated Damages — specialist ALOP cover co-ordinated with CAR / EAR / MCE engineering policies for power, infrastructure, and industrial capital projects. Call 022 4302 0000 for a specialist consultation.